# How to use Critical Path & PERT Planner

Build an ordered dependency plan, estimate task durations, and calculate the path that controls project completion. Early and late workday offsets expose float; a linked Gantt translates those results into dates.

Guide: https://gridmori.com/guides/critical-path-pert-planner

## Make your first change

1. Open **Plan**. Set the project start date in B5 to a Monday–Friday date. Dates use a five-day workweek without holidays.
2. Open **Tasks**. Replace task inputs in A8:I37. Keep predecessors above their successors; enter each predecessor’s exact ID in G:I. Blank predecessor fields mean no dependency.
3. Open **Plan**. Resolve every task warning before using the critical path. Change estimates or dependencies to test the schedule. Green bars are critical, blue bars have float, and orange marks zero-duration milestones.

Amber cells accept your entries. Green cells contain calculated results. Keep formulas, headings, and chart cells.

## Follow the example in Tasks

These are illustrative values already in the workbook. Save a copy, try one change, and then replace the examples with your own information.

- Task ID (A8): A
- Task (B8): Kickoff
- Owner (C8): Alex
- Optimistic days (D8): 1
- Most likely days (E8): 1

## Spreadsheet basics

### Save your own copy

Use File > Save As in Excel. Keep the original workbook for next time.

### Tabs and cells

Click a tab at the bottom to open it. B7 means column B, row 7.

### Type and move

Click an amber cell, type, and press Enter. Press Tab to move right.

### Choose a dropdown

Use the arrow on a validated cell to choose one of the listed options.

### Dates and amounts

Use real dates and numeric amounts. Enter 50% for half. Keep the existing formats.

### Undo a mistake

Use Ctrl+Z on Windows or Command+Z on Mac. Keep formulas, which start with =.

## Use this template well

### Replace the examples

All populated records are fictional. Replace or clear amber examples before using totals.

### Prepared capacity

30 tasks, three predecessors per task, finish-to-start links, and Mon–Fri workdays with no holidays. Predecessors must be above successors; self-links, forward links, and cycles are rejected. No lags, resource leveling, imposed deadlines, or probabilistic completion forecast. Gantt shows 20 seven-day periods.

### Blank or zero?

Leave unknown values blank. Enter 0 for a confirmed zero. Read missing-input messages before using a result.

### More records

Beyond prepared capacity, extend formulas, validation, summary ranges, and chart ranges together.

## Tabs and fields

### Plan

Set project start, review duration and critical-task counts, and inspect the 20-period Gantt.

- **Project start (B5)**: Real Monday–Friday start date. All task dates derive from it.
- **Tasks needing review (B7)**: Any entered task that fails input or predecessor checks.
- **Project workdays (B10)**: Maximum early-finish offset after a valid forward pass.
- **Critical tasks (E5)**: Tasks with zero total float, including zero-duration critical milestones.

### Tasks

Enter tasks in dependency order with three-point estimates; inspect early/late offsets, float, and dates.

- **Task ID (A8)**: Unique stable identifier. Use text IDs to avoid leading-zero ambiguity.
- **Task (B8)**: Name of the task or milestone.
- **Owner (C8)**: Person responsible.
- **Optimistic days (D8)**: Nonnegative workdays; no larger than most likely.
- **Most likely days (E8)**: Between optimistic and pessimistic.
- **Pessimistic days (F8)**: No smaller than most likely.
- **Predecessor 1 (G8)**: Exact ID of a task above this row; leave blank for no predecessor.
- **Predecessor 2 (H8)**: Optional second distinct predecessor above this row.
- **Predecessor 3 (I8)**: Optional third distinct predecessor above this row.
- **Scheduled duration (J8)**: ROUNDUP((optimistic + 4 × most likely + pessimistic) / 6, 0). All zero estimates create a milestone.
- **Early start / finish (K8)**: Zero-based workday offsets from the forward pass; finish is exclusive.
- **Late start / finish (M8)**: Backward-pass offsets using the latest project finish.
- **Total float (O8)**: Late start minus early start. Zero means critical.

Return to the Start here tab inside the workbook whenever you need these instructions.