Counting tasks can hide uneven assignments. One person may own two large tasks while another owns six quick ones. A planned-hours pivot gives the review a more useful unit without pretending to be a full scheduling engine.

Use it alongside the Gantt. The pivot groups effort by owner and status; the timeline shows when tasks overlap.

Free tutorial for small teams and spreadsheet users. Examples use English-language formulas. Modern Excel is the workbook’s target app; Google Sheets imports require feature checks. Optional templates are separate one-time purchases with their own capabilities, limits, and terms on the linked product page.

01

Define the source measure

Create a task register with unique Task ID, Task, Owner, Planned hours, and Status. Use one accountable owner per row and one consistent unit for effort. Enter planned hours for every task you intend to include.

For a small example, Alex owns a Done task of 8 hours and a Planned task of 16 hours. Sam owns a Doing task of 24 hours and a Planned task of 20 hours. The source total is 68 planned hours.

02

Create the owner-by-status pivot

Put Owner in Rows, Status in Columns, and Planned hours in Values using Sum. The example should show Alex at 24 hours, Sam at 44, and a 68-hour grand total. The Done column retains the original planned effort of completed tasks.

In Excel, refresh after changing source tasks. In Google Sheets, check the selected source range and the value aggregation. A Count result would measure tasks rather than hours and could reverse the conclusion about which assignment is larger.

03

Interpret the result within its limits

Do not label total planned hours as remaining hours. A Doing task at 50% complete still contributes its original planned effort to this pivot. Calculating remaining effort requires a separately defined estimate or method.

Likewise, 44 hours across an eight-week launch is different from 44 hours due next week. Use task dates and availability to discuss capacity. Do not assume a universal 40-hour week when owners have other work or different schedules.

04

Test an edit and a new record

Change Sam's Planned task from 20 to 28 hours. After refresh, Sam should show 52 hours and the grand total should become 76. Move the task to Doing and verify that its hours move columns while the owner and grand totals stay the same.

Add a task in the last prepared source row, assign an owner, and refresh. If it is missing, extend the pivot source before relying on the workload view. Filter blank source items and investigate unassigned work instead of treating it as spare capacity.

Official references

FAQ

Common questions

Can I split one task across two owners?

Use separately identified work packages with their own hours, or an allocation model. Repeating the full task hours for both owners double-counts the plan.

Why not sum percent complete?

Percentages for differently sized tasks are not additive. Review effort and progress with a clear weighting method rather than summing progress percentages.