Build an ordered dependency plan, estimate task durations, and calculate the path that controls project completion. Early and late workday offsets expose float; a linked Gantt translates those results into dates.

Your first five minutes

Make your first change.

  1. Open Plan

    Set the project start date in B5 to a Monday–Friday date. Dates use a five-day workweek without holidays.

    See the fields in Plan
  2. Open Tasks

    Replace task inputs in A8:I37. Keep predecessors above their successors; enter each predecessor’s exact ID in G:I. Blank predecessor fields mean no dependency.

    See the fields in Tasks
  3. Open Plan

    Resolve every task warning before using the critical path. Change estimates or dependencies to test the schedule. Green bars are critical, blue bars have float, and orange marks zero-duration milestones.

    See the fields in Plan

Amber: your entries. Type your information here.

Green: calculated results. Keep these formulas.

Status colors can change as you work. Use the field instructions below to confirm what you can edit.

Follow along in your copy

Try the example in Tasks.

The workbook already contains illustrative records so you can see how it works. Find these cells, make a small change following the first steps, and review the result before entering your own information.

A few cells to find

Task IDCell A8
A
TaskCell B8
Kickoff
OwnerCell C8
Alex
Optimistic daysCell D8
1
Most likely daysCell E8
1

These are sample values. Replace or clear the amber example cells before relying on your totals.

Critical Path & PERT Planner: the Tasks tab with illustrative sample dataOpen the worksheet preview
Tasks. The download also includes a Start here instruction tab.

New to spreadsheets?

A few things that make it easier.

Save your own copy

Use File > Save As in Excel. Keep the original workbook for next time.

Tabs and cells

Click a tab at the bottom to open it. B7 means column B, row 7.

Type and move

Click an amber cell, type, and press Enter. Press Tab to move right.

Choose a dropdown

Use the arrow on a validated cell to choose one of the listed options.

Dates and amounts

Use real dates and numeric amounts. Enter 50% for half. Keep the existing formats.

Undo a mistake

Use Ctrl+Z on Windows or Command+Z on Mac. Keep formulas, which start with =.

Keep this beside your workbook

What goes where.

01

Plan

Set project start, review duration and critical-task counts, and inspect the 20-period Gantt.

Fields in Plan. Cell references match the prepared workbook; the instructions identify inputs and calculated results.
Field and cellsWhat to do
Project start (B5)Real Monday–Friday start date. All task dates derive from it.
Tasks needing review (B7)Any entered task that fails input or predecessor checks.
Project workdays (B10)Maximum early-finish offset after a valid forward pass.
Critical tasks (E5)Tasks with zero total float, including zero-duration critical milestones.
02

Tasks

Enter tasks in dependency order with three-point estimates; inspect early/late offsets, float, and dates.

Fields in Tasks. Cell references match the prepared workbook; the instructions identify inputs and calculated results.
Field and cellsWhat to do
Task ID (A8)Unique stable identifier. Use text IDs to avoid leading-zero ambiguity.
Task (B8)Name of the task or milestone.
Owner (C8)Person responsible.
Optimistic days (D8)Nonnegative workdays; no larger than most likely.
Most likely days (E8)Between optimistic and pessimistic.
Pessimistic days (F8)No smaller than most likely.
Predecessor 1 (G8)Exact ID of a task above this row; leave blank for no predecessor.
Predecessor 2 (H8)Optional second distinct predecessor above this row.
Predecessor 3 (I8)Optional third distinct predecessor above this row.
Scheduled duration (J8)ROUNDUP((optimistic + 4 × most likely + pessimistic) / 6, 0). All zero estimates create a milestone.
Early start / finish (K8)Zero-based workday offsets from the forward pass; finish is exclusive.
Late start / finish (M8)Backward-pass offsets using the latest project finish.
Total float (O8)Late start minus early start. Zero means critical.

Make it part of your routine

Everyday use & common fixes.

Replace the examples

All populated records are fictional. Replace or clear amber examples before using totals.

Prepared capacity

30 tasks, three predecessors per task, finish-to-start links, and Mon–Fri workdays with no holidays. Predecessors must be above successors; self-links, forward links, and cycles are rejected. No lags, resource leveling, imposed deadlines, or probabilistic completion forecast. Gantt shows 20 seven-day periods.

Blank or zero?

Leave unknown values blank. Enter 0 for a confirmed zero. Read missing-input messages before using a result.

More records

Beyond prepared capacity, extend formulas, validation, summary ranges, and chart ranges together.